Skip to main content
University
of
Nebraska–Lincoln
Log In
Search
Search
Submit
Close
Midwest Roadside Safety Facility
Menu
Search
Log In
Home
Who We Are
History
Faculty/Staff
Employment
Contact Us
Services
Testing
Finite Element Analysis
Design/Consulting
Pooled Fund
About
Member States
Active Projects
Members Only
Tech Transfer
Newsletters and Featured Research
Research Hub
AFB20 (user/password required)
Pooled Fund Q&A
Q&A Home
Ask a Question
Search Questions
Q&A Reports
Login
Q&A Home
Ask Us A Question
Search Answered Questions
Q&A Reports
Login
Nebraska
MwRSF
Q&A Home
Seach Q&A
View Q&A
View Q&A
End Treatment Gaps
Question
State
MO
Description Text
MoDOT has a situation where the roadway guardrail and the ramp guardrail come close together at the nose of the gore. Have you any experience or knowledge of what is the required or recommended gap between the two end treatment (ex. ET 2000) to work properly?
System Performance Evaluation
System Types
Road Closure Gates
Thrie Beam Guardrails
Applications
System Features
Date
August 26, 2004
Previous Views (126) Favorites (0)
Response
Response
(active)
Two different approaches are available for treating the situation described above. First, one could install end treatments that bring both guardrails into a single terminal system, such as used in the FLEAT-MT and CAT. Second, one could use any of the energy-asborbing guardrail end terminals on each guardrail end but with ending the back-side system approximately 50 ft downstream of the first system. If option two is used, all guardrail posts exposed on the back side of the first terminal must be treated with breakaway guardrail posts in order to avoid excessive wheel snag concerns and the potential for vehicle rollovers.
Date
August 31, 2004